‘Contractors abandoned road construction, rehabilitation after payment of N184bn’ – Senator Mpigi

A National Assembly joint committee has revealed the names of road contractors who allegedly failed to complete or commence work despite receiving funds from the government.

This disclosure occurred during the budget defense session for the 2024 fiscal year by the Federal Ministry of Works, where the Minister of Works, David Umahi, led ministry officials to appear before a joint committee of the House of Representatives and the Senate on Works.NYSC Portal


👉 Relocate to Canada Today!

Live, Study and Work in Canada. No Payment is Required! Hurry Now click here to Apply >> Immigrate to Canada

Minister Umahi explained that in the 2023 fiscal year, the defunct Federal Ministry of Works and Housing was allocated a budget of N534.4 billion, with N383.3 billion allocated to the Federal Ministry of Works after the merger. However, only a small sum of N184.16 billion was released by the Federal Government for capital expenditure.

See Other Top Stories:

Upon inquiries from committee members, Senator Barinada Mpigi, the committee’s chairman, asked Minister Umahi to provide information on the utilization of the 2023 budget allocation before addressing the 2024 budget performance.

Umahi responded by stating that the funds allocated for 2023 had been effectively used for road and bridge projects.informationguidenigeria

He said: “The sum of N184,165,147,332.29 released up to date to the Ministry from the 2023 Budget Appropriation had been utilised for payments of some certified certificates for executed works on roads and bridges by highway, projects of Engineering Services and Common Services departments.

“It is to be noted that as of the end of November 2023, the ministry had a cumulative unpaid certificate in the sum of N1,507,873,365,516.02 (One Trillion, Five Hundred and Seven Billion, Eight Hundred and Seventy-three Million, Three Hundred and Sixty-five Thousand, Five Hundred and Sixteen Naira, Two Kobo) only for all inherited ongoing highway and bridge projects.”

The chairman of the Senate Committee on Works, Senator Barinada Mpigi, representing Rivers South-East senatorial district, said:JAMB Result

He said: “I want the press to hear me out. The contractor handling Aba-Owerri Road through NNPC Depot Express, Abia State, has been mobilised, and as we speak, he has not done any work. We don’t want to mention his name here. They have collected the sum of N76 million.

👉 Relocate to Canada Today!

Live, Study and Work in Canada. No Payment is Required! Hurry Now click here to Apply >> Immigrate to Canada

“The rehabilitation of roads in Kebbi State is being handled by Setraco. The company collected over N400 million and is presently not on site. In Ogun State, the contractor has collected over N25 million and has not been seen on site since then. The name of the contractor is HMF Construction Limited; the rehabilitation of the Asaba-Agbor dual carriageway [is being handled] by Heartland Construction Limited. They were paid the sum of N50 million and have not been seen.JAMB Portal

“For the construction of the Bida-Pategi bridge across the River Niger in Niger State, the contractor has collected N400 million and he is not on-site; the construction of two-kilometre asphalt to Nnamdi Azikiwe University Teaching Hospital Nnewi-Oraifite in Anambra State by Zeerock Habitation International Services Nigeria Limited, the company collected over N97 million with zero performance; for the rehabilitation of kilometre 1, Bende road in Abia State linking Akwa Ibom, as we speak, he has been paid over N445 million. The name of the contractor is Defensive and Protective Concept Limited, with nil performance.

“We have more of this in Niger; we have more of this in Nasarawa; and we have it in the North East. In the North East, we have rehabilitation on Maiduguri-Gongola Road. The contractor’s name is Comet Nigeria Limited. The contractor collected over N3 billion. The contractor is not on site. The physical progress of that project is 0.88%.”

He continued: “In Bauchi, construction and rehabilitation of Wuyashi-Kakuri-Yauri Road, the contract number is 7639 which has been mobilised with over N12 billion. The contractor is not on site and so many others.”

Check JAMB Result

Check and Confirm: How much is Dollar to Naira

📢 We are hiring writers!

Article Writing Jobs - We are hiring good freelance writers - Click here to apply

Copyright Warning!

Contents on this website may not be republished, reproduced, or redistributed either in whole or in part without due permission or acknowledgment. . Proper acknowledgment includes, but not limited to (a) LINK BACK TO THE ARTICLE in the case of re-publication on online media, (b) Proper referencing in the case of usage in research, magazine, brochure, or academic purposes,. . All contents are protected by the Digital Millennium Copyright Act 1996 (DMCA). . . The images, except where otherwise indicated, are taken directly from the web, if some images were inserted by mistake violating the copyright, please contact the administrator for immediate removal.
. We publish all content with good intentions. If you own this content & believe your copyright was violated or infringed, please contact us  for immediate removal.

Emediong Silver

Emediong Ekpe is a graduate of English. A professional Sports journalist/analyst, and a spoken word artist. He is passionate about decimating information and putting smiles on people's faces via news writing. Whatapp: 08088735884

Related Articles

Leave a Reply

Your email address will not be published. Required fields are marked *

Back to top button

It looks like you're using an ad blocker!

This website InfoGuideNigeria.com is maintained by the advertising revenue and we noticed you have ad-blocking enabled. Please disable Ad-Blocker